On January 1, 2026, new SOLAS Regulation II-1/3-13 entered into force, establishing mandatory requirements for the design, construction, testing, and maintenance of lifting appliances . While these regulations primarily target maritime applications, they set a benchmark for lifting equipment safety that theatrical venues and stage winch manufacturers cannot afford to ignore. This guide examines the new requirements and their implications for stage winch users and suppliers.
Not directly, but they set a new safety benchmark. SOLAS Regulation II-1/3-13 applies specifically to lifting appliances on ships of 500 gross tonnage and above engaged in international voyages. However, the standards introduced—including mandatory load testing, documented safe working load (SWL) marking, periodic thorough examinations, and redundant safety systems—represent best practices that entertainment venues and regulatory bodies are increasingly adopting. For a Pilewind Stage Winch manufacturer, aligning with these standards demonstrates commitment to safety and positions products for venues that require the highest levels of certification.
New SOLAS requirements apply to lifting appliances installed on or after January 1, 2026
The new SOLAS regulation establishes comprehensive requirements that apply to all lifting appliances and anchor handling winches. Key provisions include:
For lifting appliances installed before January 1, 2026, the regulation requires compliance no later than the date of the first Safety Construction Renewal Survey on or after that date. This means existing installations have a grace period but must eventually meet the new standards.
Importantly, the regulation allows for existing appliances with valid certificates under other international instruments (such as ILO Convention No. 152) to be considered compliant until those certificates expire. However, for appliances where SWL is undocumented and design information is unavailable, the test load must be calculated based on a SWL nominated by the company, subject to recognized organization approval.
| Requirement | New Installations (On/After 01/01/2026) | Existing Installations (Before 01/01/2026) |
|---|---|---|
| Design & Construction Standards | Must comply with RO requirements | Grandfathered, but must comply by first renewal survey |
| Load Testing | Required after installation | Required by first renewal survey on/after 01/01/2026 |
| SWL Marking | Permanently marked | Permanently marked by first renewal survey |
| Periodic Retesting | Every 5 years | Every 5 years from first compliance |
| Annual Thorough Exam | Required | Required |
While SOLAS applies to maritime applications, the standards it introduces are becoming benchmarks for lifting equipment safety across industries. For stage winch manufacturers and venues, the implications are clear:
Ensure all lifting appliances meet recognized organization standards. Maintain documentation of design approvals and SWL certification.
Conduct load tests after installation and before first use. Permanently mark SWL on each appliance and maintain documentary evidence.
Perform annual thorough examinations and five-yearly load retests. Maintain records of all inspections and tests on board.
The Gaiety Theatre in Ayr, Scotland, provides a practical example of safety-compliant Pilewind winch installation. Four 500kg units were installed with slack line sensors, overload sensors, standard and over-travel limits, and dual control panel safety interlocks. These features align with the safety principles underpinning the new SOLAS requirements, demonstrating that modern stage winches already incorporate many elements of the emerging global safety framework.