Home / News / Industry News / Mobile Zero-Fleet Stage Winch Project Planning: Layout & Installation Guide

Industry News

Mobile Zero-Fleet Stage Winch Project Planning: Layout & Installation Guide


Load-in day at a 1,200-seat multi-purpose hall. The fly tower tops out at 12 m, the lighting design calls for a 9.5 m batten with 14 independently motorized points, and the polished concrete floor must host a corporate dinner the next evening. There is no time to build a permanent grid; there is one weekend to turn the room into a theatre. This is the scenario where mobile zero-fleet stage winches are planned from the first site survey, not introduced as a fallback.

RenteZhihe (JiangSu) Equipment Technology Co., Ltd. builds the winches, but the venue team and the installer decide whether the layout succeeds. Load paths, floor preparation, power drops, and control architecture are the decisions that separate a clean load-in from a stop-work incident, and they are made before the first unit leaves its flight case.

What Makes a Mobile Zero-Fleet Stage Winch Different from a Fixed Winch

A mobile zero-fleet stage winch is a portable hoisting unit whose single-layer grooved drum holds the wire rope at a 0 degree fleet angle, so the load point stays horizontally fixed across the full travel distance.

50 kNMaximum rated line pull in the mobile range
25 mSingle-layer rope travel per drum
1.2 mBase footprint for wing-space placement
2 mmBase leveling tolerance before rigging

A standard drum winch with a 1.5 degree fleet angle pulls the load roughly 400 mm sideways over a 20 m lift. Fixed structures tolerate that drift; portable units rigged to batten trim marks do not. The zero-fleet drum removes the geometry problem mechanically instead of asking software to compensate for it.

Lateral load drift over a 20 m lift
Standard drum winch
400 mm
Zero-fleet winch
0 mm
  • Line pull ratings from 10 kN to 50 kN across the mobile product family
  • Single-layer rope travel up to 25 m per drum before rewinding
  • Footprints from 1.2 m by 1.2 m for standard wing and dock positions
  • Unit mass from about 350 kg to 900 kg fully dressed with cable
0 degree fleet angle means zero lateral load drift over a 25 m single-layer lift
Mobile Zero-Fleet Stage WinchMobile Zero-Fleet Stage WinchRedefining portable stage machinery, the Mobile Self-Tailing Winch features a sleek, compact design tailored for solo lifting points on the go. Driven by a servo syste...View Product →

Layout Planning: Start with the Load Path, Not the Winch Position

The load path is the continuous chain from the suspended batten through the wire rope, drum, winch frame, base plate, and dunnage into the floor slab, and every layout position must pass that chain test. The most common error is placing winches where power outlets already exist and bending the rigging plan around the architecture. Fix the batten positions first, work backwards to the winch, then bring power and data to the unit.

If the venue team needs a second opinion on spacing, request a layout review before the contract locks the load positions onto the drawings.

Fixed fly tower layout

  • Dedicated machinery room beside or below the stage
  • Steel grid carries the load; the floor stays free
  • Headroom fixed by the building structure
  • Installation finished weeks before the show

Mobile zero-fleet layout

  • Stage floor or wing space holds the winches
  • Slab and dunnage carry the load
  • Headroom depends on rope deflection clearance
  • Installation finished days before the show

Footprint and Headroom Checks

Where wing space is tight, an inline zero-fleet winch keeps the rope axis aligned with the haul direction, so the unit sits in a corridor instead of reshaping the rigging plot. Both standard and compact variants need the same minimum deflection radius above the drum, so confirm headroom before committing to a position.

In-Line Zero-Fleet Stage WinchIn-Line Zero-Fleet Stage WinchThe “Single” series represents the pinnacle of intelligent winch design, featuring a unique dual-encoder system paired with a dual-brake motor for pinpoint accuracy. D...View Product →
Minimum acceptance values for mobile zero-fleet winch layout surveys.
Check item Target value Why it matters
Slab load at each dunnage foot 5 kN or below after spreading Prevents surface micro-cracking
Distance from unprotected deck edge 600 mm or more Preserves edge shear capacity
Rope deflection radius 300 mm minimum Prevents wire fatigue and abrasion
Lateral anchor capacity 1.5 times rated pull Covers hard stops and dynamic sway

Civil and Structural Preparation: Slab Ratings, Power Drops, and Access

The floor slab is the foundation of a temporary rigging system; if it cannot carry the projected point loads at the marked positions, the plan fails before installation. A 900 kg winch pulling a 2,500 kg batten can put nearly 1.5 tonnes on each dunnage foot during worst-case braking. A reinforced concrete slab rated at 5 kN per square centimetre absorbs that easily; a 20 mm screed layer over insulation does not.

Floor and Anchoring Preparation

Shim every winch base to plus or minus 2 mm of level. Anchor bolts provide lateral stability; where the venue forbids drilling, a ballasted base of concrete blocks or steel plates must match the same anchor capacity calculated for the floor.

Power and Data Drop Locations

Each winch needs a 400 V three-phase circuit at 32 A with a protective earth. Data runs travel in separate trays, and the emergency-stop loop follows its own route. Mark every drop during the survey so installation crews are not cutting floor covers on load-in day.

Cabling and Control Integration on a Temporary Grid

A temporary rigging network must carry the same safety architecture as a permanent installation: a closed-loop emergency-stop chain, certified limit switches, and real-time position feedback. Power, data, and the safety loop are three separate paths and never share a conduit bundle.

Multi-axis synchronization runs over EtherCAT or an equivalent industrial protocol because the round-trip latency of that link decides whether 14 winches keep one batten level. The emergency-stop chain uses monitored continuity; an open loop freezes all axes within 200 ms. For cues above normal speed or sub-millimetre positioning, the servo-driven zero-fleet winch is the unit specified.

Servo-Driven Zero-Fleet Stage WinchServo-Driven Zero-Fleet Stage WinchFor applications demanding the ultimate in speed and precision, the Servo Series Stage Winch is the answer. Driven by an advanced electric servomotor, it boasts an ult...View Product →

Installing Mobile Zero-Fleet Stage Winches: Seven Steps That Prevent Rework

The field-proven sequence is survey, position, rig, terminate, test, proof-load, and program; skipping one step to save an hour adds a day of rework.

  1. Pre-install survey: confirm slab rating, power drops, and marked positions.
  2. Place and level: set the dunnage, lower the winch, and shim the base to plus or minus 2 mm.
  3. Rig the rope: reeve wire rope, set the limit switch cam, and connect the batten hardware.
  4. Terminate services: wire power, data, and the emergency stop; verify loop continuity before power-on.
  5. Run safety tests: open the emergency stop twice, confirm all axes stop, and test slack-line sensors.
  6. Proof-load the system: apply 1.25 times rated load for 10 minutes, then re-check anchors and rope.
  7. Program and rehearse: load the position table, run a full show cycle twice, and log the results.

A dedicated stage machinery installation and commissioning service can run the complete sequence for an eight-winch layout in two and a half days on a prepared floor.

The proof-load test is the moment of truth: the rope, the anchorage, and the slab are proven together before the show clock starts.

Safety Standards and Documentation That Follow the System Out of the Building

Mobile zero-fleet winches sit under the same machinery safety framework as fixed winches: wheels change the installation, not the safety classification. Most venue jurisdictions accept documented compliance with EN 17206 acceptance testing and the applicable machinery directive, with control risk assessments aligned to SIL logic. Ask the supplier for the Declaration of Conformity, load test certificate, inspection log templates, and operator training records as part of the delivery package.

  • Declaration of Conformity for every winch shipped to site
  • Load test certificate with the date and the proof weight used
  • Daily inspection log covering rope, limit switches, and brake function
  • Operator training and competency record retained by the venue
The standards do not weaken because the winch has casters.

Frequently Asked Questions on Mobile Zero-Fleet Winch Planning

Can mobile zero-fleet stage winches be used on uneven or temporary floors?

No. Level the base to plus or minus 2 mm before rigging. On concrete use steel shims; on event decks build a plywood and dunnage platform; on outdoor ground use spreader plates and verify the bearing capacity.

What power supply does a mobile zero-fleet stage winch need?

Each unit typically needs a 400 V three-phase supply at 32 A with a protective earth. Arrange power drops before load-in; cables routed through doorways create trip and damage risks that safety audits will flag.

Can mobile winches connect to an existing show control system?

Yes. The winches accept EtherCAT, PROFINET, and digital I/O interfaces. The connection is commissioned together with the emergency-stop chain and verified during the proof-load sequence.

How long does a typical mobile winch installation take?

An eight-winch layout on a prepared floor with power and level positions is installed, tested, and programmed in two and a half days. Add a full day when site preparation is not complete.


+86-139 1771 1698

rtstage@163.com